Practice Areas

Construction Law

Legal advice and representation in the conclusion and performance of construction contracts, in disputes between project owners, contractors and other parties involved in construction, in pursuing claims for defective work, delays and unfulfilled contractual obligations, and in other legal matters relating to construction.

How I can help

  • drafting, reviewing and negotiating construction, design and other construction-related contracts
  • advice on the rights and obligations of project owners, contractors and subcontractors
  • pursuing claims for defective construction work
  • claims arising from delays, additional and unforeseen works, and changes to contractual obligations
  • disputes over valuations and final accounts for work carried out, unpaid amounts and withheld payments
  • representation in court proceedings and out-of-court resolution of construction disputes

Construction disputes in Slovenska Bistrica and the surrounding area

My office is in Slovenska Bistrica, at Ljubljanska cesta 69. I advise project owners, contractors and subcontractors from Slovenska Bistrica, Oplotnica, Poljčane, Makole and elsewhere. I advise in Slovenian and English, which helps foreign nationals who are building or renovating a property in Slovenia. I represent clients before the court in Slovenska Bistrica, the Maribor District Court (Okrožno sodišče v Mariboru) and other courts and authorities in the Podravska and Savinjska regions (Maribor, Ptuj, Celje) and throughout Slovenia, because a court's jurisdiction depends on statutory rules, not on where a lawyer's office is.

The first question in any construction dispute is which procedural rules apply. Where, for example, both parties are companies, or the dispute is between a sole trader and a company and arises from the sole trader's business activity, the rules on commercial disputes apply (Article 481 of the Civil Procedure Act, ZPP). Commercial disputes are heard at first instance by a district court, whatever the value in dispute (Article 32 ZPP). A dispute between a private homeowner and a contractor follows the general rules of civil procedure. From 1 January 2027 the court in Slovenska Bistrica becomes an external department of the Maribor District Court; documents can still be filed in Slovenska Bistrica, and the place of the hearing in new cases will be stated in the summons.

How we work together and what to prepare

In construction disputes the documents are decisive. Please bring the contract or accepted quotation with any annexes, the design documentation, interim and final accounts, invoices and proof of payment, the record of handover, and the e-mails and photographs that show how the work progressed and where the defects are. If a site diary (gradbeni dnevnik) or a book of measurements (knjiga obračunskih izmer) was kept, bring those too. On that basis I explain your rights and obligations, which deadlines are running and what further evidence will be needed.

Under the Obligations Code (OZ), a construction contract must be concluded in writing (Article 649), and a contractor needs the client's written consent for any departure from the construction plans or the contracted works (Article 652). In disputes over additional works it therefore matters how the change was agreed and recorded – see my article in Slovenian on payment for additional works. If a defect has to be repaired quickly, evidence should be secured first: even before proceedings begin, a party can ask the court to take evidence where there is a justified fear that it could not be taken later or would be harder to take (Article 264 ZPP).

We first consider out-of-court options – a reasoned written demand, negotiation or a settlement. If no agreement is possible, I prepare the claim or the defence and represent you in the proceedings. Where establishing the facts, for example the quality or value of the work, requires specialist knowledge the court does not have, the court takes evidence from an expert (Article 243 ZPP). Where a dispute also concerns ownership or the land register (zemljiška knjiga), it overlaps with real estate law. You can arrange a meeting through the contact page.

Deadlines for defects and other common issues

Ordinary defects in the work must be distinguished from defects affecting the structural soundness of a building. Unless the construction contract rules provide otherwise, liability for defects follows the rules on contracts for work (Article 660 OZ). The client must inspect the work as soon as is normally possible and notify the contractor of any defects without delay (Article 633 OZ). A hidden defect must be notified as soon as possible and within one month of its discovery at the latest, and no defects can be relied on more than two years after acceptance of the work (Article 634 OZ). Court action must then be brought within one year of the notification (Article 635 OZ).

For defects affecting structural soundness, the contractor is liable if they appear within ten years of handover and acceptance of the work, and this liability extends not only to the client but also to later acquirers of the building (Article 662 OZ). The client or acquirer must notify such a defect within six months of discovering it, and the right expires one year after the notification (Article 663 OZ).

Price disputes are also common. Under a “turnkey” (ključ v roke) clause, the agreed price includes the value of all unforeseen and additional works (Article 659 OZ). Unless the contract says otherwise about price changes, a contractor who has completed the work on time may ask for a price increase if the cost of the elements on which the price was based has risen so much that the price would be more than two per cent higher – but only for the difference above that threshold (Article 655 OZ). The contractor is entitled to fair payment for urgent unforeseen works (Article 653 OZ). Claims under commercial contracts become time-barred after three years (Article 349 OZ), while the general limitation period is five years (Article 346 OZ). Which deadlines apply always depends on the type of contract and the circumstances.

Frequently asked questions

When do I need a construction lawyer in Slovenia?

It makes sense to involve a lawyer before signing a construction contract, while the price, deadlines, acceptance of the work, liability for defects and the procedure for additional works can still be set out clearly. Legal advice is also useful once a dispute has arisen – over defects, delays, a rejected final account or withheld payment. At that point the documents need to be reviewed and the deadlines for notifying defects and for limitation checked. Whether representation is needed depends on the value and complexity of the matter.

What can I do if the contractor does not fix the defects?

The client must notify the contractor of the defect in time. Unless the defect makes the work unusable, the client must let the contractor remedy it and may set a reasonable deadline. If the contractor fails to do so, the client may have the defect repaired at the contractor's expense, reduce the price or withdraw (not for a minor defect), and may always claim damages (Article 639 of the Obligations Code). If the work is unusable, the client may withdraw without first requesting a repair (Article 638).

Does the client have to pay for additional works that were not confirmed in writing?

A contractor needs the client's written consent for any departure from the construction plans or the contracted works; without it, no increase of the agreed price can be claimed (Article 652 of the Obligations Code). Urgent unforeseen works needed to keep a structure stable or prevent damage are different: the contractor may carry them out without prior consent if the urgency made it impossible to obtain, but must notify the client immediately (Article 653). Whether payment is owed depends on the circumstances and the evidence of what was ordered.

How long is a contractor liable for defects in a new building?

For defects affecting structural soundness, the contractor is liable if they appear within ten years of handover and acceptance of the work. The same applies to the designer where the defect stems from the plans. Both are also liable to later acquirers of the building, and this liability cannot be excluded or limited by contract (Article 662 of the Obligations Code). Notice must be given within six months of discovering the defect, and the right expires one year after notice is given (Article 663). Shorter deadlines apply to other defects.

What can a subcontractor do if the main contractor does not pay?

A subcontractor's claim lies primarily against the contractor it has a contract with, and it can be pursued through a written demand, an enforcement application or a court claim. The Obligations Code also allows the contractor's collaborators to turn directly to the client for acknowledged claims and request payment out of the amount the client owes the contractor at that moment (Article 631). Under the authentic interpretation of that article, both claims must relate to work under the same contractual relationship. Whether this applies depends on the circumstances.

These answers are general and do not replace legal advice on your matter, which depends on its specific circumstances.